Applicant
BPM Application Process For Material Master Data Maintenance
Use T-code MM60 in SAP to make sure what action needs to be done
End
BPM informs applicant and relevant departments by email
BPM informs engineering by email to implement the task
Click refill
Engineering implement the task in SAP and submit the task in BPM
BPM informs applicant to refill the information
BPM informs engineering by email to approve
Click approve in BPM
Check information is sufficient
Start
Register relevant information in BPM and click submit
Applicant & Relevant Dept.
Engineering