THEHASSIMESSAOUDREFINERYPROJECTSTORAGETANKS
2021-05-12 16:35:27 0 举报
AI智能生成
国际EPC工程项目工作分解过程(WBS)
作者其他创作
大纲/内容
Project Management
Project Management Team
Project Management Plan
BIM Management
Kick - off Meeting
Detailed Engineering
Mechanical Calculation
Overturning stability
HYDRAULIC / PNEUMATIC CALCULATIONS
Roof, Shell and Bottom Plates
Other accessories like top angle, stiffeners,etc
Roof Calculation
Structure Calculation
Floating Roof Floatability
FEA Calculation
Local shell and Roof Stress
Local stress check of external loads
Foundation Calculation
Anchor Bolts
Verification of moment and shear load
fabrication detail drawings
calculation report
detail drawings
appurtenance drawings
internal and external drawings
Erection Drawings
As-built documents
Calculation of Appurtenance
Calculations for vents
helicoidal stairs and ladders
internal loads on nozzles
Roof and shell platforms,
Overpressure protection
emergency vents
All necessary complementary calculations
Design of Special Parts
Tank Side Entry Mixers
Tank Jet Mixers
MP/LP Steam Coils
Hot Oil Coils
Oxygenation Air Diffuser
Documentation and Authority approval/certification
ARH/DGM
ONML
The other Authority(If applicable)
Procurement
Equipment and materials
Shell,roof and bottom plates
Internal and External Appurtenances
Painting System
Installation equipment and tool
Subcontractors
Design subcontracting
Fabrication subtractor
Transportation Subtractors
Installation subcontractor
Other subtractors
Consultation
Local Legal advisor
Local Project Advisor
Engineering advisor
Installation advisor
Local Public relation Advisor
Field Erection
Preparation of Installation
Preparation of temporary facilities
Preparation of Installation Documents Required
On-site investigation
Site Work Permits
Verification of tank foundation
Mobilization at SITE
80080 Hassi Tanks South
UPSIDE-DOWN ERECTION METHOD
0510 FUEL OIL (FOS)
Tank (Steel) Plate Welding Work
Roof Installation
NDE
Tank Accessories and Miscellaneous
Tank Hydrotest
Internal & External Painting Work
S530 RAW WATER TANK (RWT)
S630 INTERMEDIATE PRODUCT STORAGE (IPT)
S640 FINAL PRODUCT BLENDING, STORAGEG
80080 Hassi Tanks North
UPSIDE-DOWN METHOD(Except 0595 and 0620)
0420 AMINE REGENERATION (ARU)
0440 SOUR WATER STRIPPER (SWS)
N530 RAW WATER SYSTEM (RWS)
0540 DEMI WATER (DEW)
0560 SERVICE WATER (SRW)
0595 FIREWATER & FIREFIGHTING (FWS)
Upright Erection Method
0620 CRUDE OIL METERING AND STORAGE (COT)
Upright Erection Method
N630 INTERMEDIATE PRODUCT STORAGE (IPT)
QUALITY, INSPECTION AND TEST
Material certification
Weldering tests
Non Destructive Examination
Hydrostatic test,
pneumatic test,
Other tests
HSE Management
Precommissing and Take-over
Precommissing Test
Take-over Certification
Dismental of Temporary Facilities on site
Project Settlement