Building Department Consent flow chart (A&A Works)
作者其他创作
大纲/内容
* Type II Works refer to PNAP-APP97
14 Days
30 Days
Day 1
Site Inspection
Plan & Consent approved
-Submit GBP -Form BA4 to6
Report Completion (BA14)
Disapproved
Apply Consent(Form BA8)
Accepted
60 Days
Day 61
Normal Procedure
Site Works
Acknowledgement Letter for completion
Day 90
Notice of Commencement (BA10)
-Submit GBP span style=\"font-size: inherit;\
BD processing
Day 97
Normal Procedure w./ concurrent
approved
Not Accepted
Plan approved only
Day 62
Day 31
28 Days
Day 67
Day 32
-Submit GBP -Form BA4 to6_-Form BA8a
Building Department Submission Procedure
Day 37
Fast Track w./ concurrent (Type II Works eg. Repair Glass Wall)