CSCI883 项目管理 project managerment
作者其他创作
大纲/内容
1
Intro System Analysis and Design
Infomation technology
Five elements in an information system:
Hardware, Software, Data, Processes, People
Hardware, Software, Data, Processes, People
SDLC
1. Identify the problem or need and obtain approval
2. Plan and monitor the project, i.e., what, how and who
3. Discover and understand the details of the problem or need
4. Design the system components that solve the problem
5. Build, test, and integrate system components
6. Complete system tests and then deploy the solution
2. Plan and monitor the project, i.e., what, how and who
3. Discover and understand the details of the problem or need
4. Design the system components that solve the problem
5. Build, test, and integrate system components
6. Complete system tests and then deploy the solution
System Analyst
General approach to problem solving
- Research and understand the problem. 研究和了解问题
- Verify that the benefits of solving the problem outweigh the costs. 验证解决该问题的好处是否大于成本。
- Define the requirements for solving the problem. 定义解决问题的要求。
- Develop a set of possible solutions(alternatives) 制定一套可能的解决方案(替代方案)
- Decide which solution is best, and make a recommendation. 决定哪种解决方案是最好的,并提出建议。
- Define the details of the chosen solution. 界定所选解决方案的细节。
- Implement the solution. 实施解决方案。
- Monitor to make sure that you obtain the desired results. 监测以确保你获得预期的结果。
分析师具备的知识和技巧
分析师相关职业
IT项目管理
Project、Job、exploration的区别
System Analysis and System Design
项目属性
Project Attributes
Project Attributes
- has a unique purpose
- is temporary
- is developed using progressive elaboration
- requires resources, often from various areas
- should have a primary customer or sponsor
- involves uncertainly
项目约束
Project constraints
Project constraints
scope
cost
time
• Quality
• Resources
• Risk
• Resources
• Risk
项目成功
Project Success
Project Success
什么是项目管理?
- the application of knowledge, skills, tools and techniques to project activities to meet project requirements
- meet the triple constraint
使项目满足需求
Project Management Tools and Techniques
Project charter (integration)
Scope statement, and WBS (scope)
Gantt charts, network diagrams, critical path analysis (time)
Cost estimates and earned value management (cost)
Fishbone diagrams (quality)
项目管理员要具备的技能
2
The project management and IT context
Projects Cannot Be In Isolation
一个项目是公司所有产品研发的一个部分
Systems Approach
Systems philosophy系统理念: an overall model for thinking about things as systems
Systems analysis系统分析: problem-solving approach
Systems management系统管理: address business, technological, and organizational issues before making changes to systems
Three-Sphere Model
Business issues
Technological issues
Organizational issues
project life cycle
项目生命周期是一个项目阶段的集合,定义了
在每个阶段将进行哪些工作
哪些成果将在何时产生
每个阶段的参与者是谁,以及
管理层将如何控制和批准每个阶段的工作。
在每个阶段将进行哪些工作
哪些成果将在何时产生
每个阶段的参与者是谁,以及
管理层将如何控制和批准每个阶段的工作。
Deliverable 可交付成果
Project Phases
Early phase
Middle phase
Final phase
Middle phase
Final phase
Recent Trends Affecting IT Project Management
Globalization: 由于大型跨国公司的影响和通信的改善,世界上不同的文化和经济体系正变得相互联系和相似。
Communications
Trust
Trust
Outsourcing(外包=Offshoring离岸外包): is when an organization acquires goods and/or sources from an outside source.
Isolating team members
Communication
Communication
Virtual Teams: A virtual team is a group of individuals who work across time and space using communication technologies.
Trust and relationships
Leadership
Conflict management
3
project integration management
项目集成管理
项目集成管理
What is Project Integration Management?
项目集成管理是影响所有其他知识领域的首要功能,同时也受所有其他知识领域的影响。
战略规划和项目选择(筛选项目和分析项目价值)
Strategic Planning and Project Selection
Strategic Planning and Project Selection
1. identify potential projects
Organizations often perform a SWOT analysis by using mind mapping
Organizations often perform a SWOT analysis by using mind mapping
Analyzing Strengths
Weaknesses,
Opportunities
Threats
2. use realistic methods to select which projects to work on
(Methods for selecting projects)
(Methods for selecting projects)
• Focusing on broad organizational needs
Need
Funding
Will
• Categorizing information technology projects
• Performing net present value or other financial analysis
• Using a weighted scoring model
3. formalize project initiation by issuing a project charter
what is project charter?
- 项目章程是一份正式承认项目存在的文件,为项目的目标和管理提供指导。
- 它授权项目经理使用组织资源来完成该项目。
- 主要的项目利益相关者应该签署项目章程,以确认对项目的需求和意图的认同。
项目章程中的Basic Information
- The project’s title and date of authorization项目的名称和授权日期
- The project manager’s name and contact information项目经理的姓名和联系信息
- A summary schedule, including the planned start and finish dates一份简要的时间表,包括计划的开始和结束日期
- A summary of the project’s budget or reference to budgetary documents项目的预算概要或预算文件的参考资料
- A brief description of the project objectives项目目标的简要描述
- Project success criteria项目的成功标准
- A summary of the planned approach for managing the project管理项目的计划方法的摘要
- A roles and responsibilities matrix角色和责任矩阵
- A sign-off section for signatures of key project stakeholders供主要项目利益相关者签名的签字部分
- A comments section in which stakeholders can provide important comments related to the project评论部分,利益相关者可以提供与项目有关的重要评论
why develop project chapter?
• A project charter secures support from top management and key stakeholders.
• A project charter reduces project failure risk relating to unclear requirements
and expectations.
• A project charter ensures proper planning and communications.
• It is important to get people with the proper knowledge and authority to write
and sign the project charter.
• A project charter reduces project failure risk relating to unclear requirements
and expectations.
• A project charter ensures proper planning and communications.
• It is important to get people with the proper knowledge and authority to write
and sign the project charter.
4
Project Scope Management
项目范围管理
项目范围管理
什么是Scope?
all the work involved in creating the products of the project
创建项目产品所包含的所有工作,就是要完成这个项目要做哪些工作
创建项目产品所包含的所有工作,就是要完成这个项目要做哪些工作
什么是项目范围管理?
就是提前将项目开发中要做的工作,项目完成时间,完成时要交付哪些东西提前写清楚
Main processes
1. Collection requirements
项目的规模、复杂性、重要性和其他因素会影响到在收集需求上花费多少精力。
项目的规模、复杂性、重要性和其他因素会影响到在收集需求上花费多少精力。
2. Defining scope
project scope statement
项目范围说明书
随着时间的推移,项目的范围应该变得更加清晰和具体
项目范围说明书
随着时间的推移,项目的范围应该变得更加清晰和具体
• Product scope description
开发产品需要做的工作量描述
开发产品需要做的工作量描述
• Product user acceptance criteria
产品用户验收标准
产品用户验收标准
• Detailed information on all project deliverables
可交付产品信息描述(分多个交付阶段)
可交付产品信息描述(分多个交付阶段)
3. Creating the WBS
Decomposition is the main tool or technique for creating a WBS
• Subdividing project deliverables into smaller pieces
• A work package is a task at the lowest level of the WBS
• Subdividing project deliverables into smaller pieces
• A work package is a task at the lowest level of the WBS
The project management plan, project documents, enterprise environmental factors, and organizational process assets are the primary inputs for creating a WBS.
项目管理计划、项目文件、企业环境因素和组织流程资产是创建WBS的主要输入。
项目管理计划、项目文件、企业环境因素和组织流程资产是创建WBS的主要输入。
4. Validating scope
验证范围包括正式接受项目的可交付成果。
5. Controlling scope
objective Vs goal
目的 Vs 目标
目的 Vs 目标
objective比goal更具体,更有针对性。
objective是可衡量的,因为它是较低层次的陈述,可以在项目结束时进行评估,看它是否实现。
我们必须假设该objective是可以实现的,而且是相关的。
objective是基于时间的,例如,应在12月31日前完成
objective是可衡量的,因为它是较低层次的陈述,可以在项目结束时进行评估,看它是否实现。
我们必须假设该objective是可以实现的,而且是相关的。
objective是基于时间的,例如,应在12月31日前完成
制定objective的规则-----SMART rule
• S— specific, that is concrete and well-defined 也就是具体的和明确的
• M— measurable, that is, satisfaction of the objective can be objectively judged 可以客观地判断目标的满意度
• A— attainable/achievable, that is, it is within the power of the individual or group concerned to meet the target 个人或团体有能力达到目标
• R— relevant, the objective must relevant to the true purpose of the project目标必须与项目的真正目的相关
• T— time-based, that is, there is defined point in time by which the objective should be achieved 有明确的时间点,应在此基础上实现目标
• M— measurable, that is, satisfaction of the objective can be objectively judged 可以客观地判断目标的满意度
• A— attainable/achievable, that is, it is within the power of the individual or group concerned to meet the target 个人或团体有能力达到目标
• R— relevant, the objective must relevant to the true purpose of the project目标必须与项目的真正目的相关
• T— time-based, that is, there is defined point in time by which the objective should be achieved 有明确的时间点,应在此基础上实现目标
5
项目进度管理
Project Schedule Management
Project Schedule Management
what? 确保按时完成项目。
Stpe
1. Planning schedule management
2. Defining activities
Activity list
Activity attributes
3. Sequencing activities
按依赖关系、优先级关系排序活动
按依赖关系、优先级关系排序活动
依赖的理由
Mandatory dependencies
Discretionary dependencies
External dependencies
Internal dependencies
Network Diagrams
网络图是显示活动排序的首选技术
Two main formats:
Two main formats:
- Activity-on-arrow (AOA) or Arrow Diagramming Method (ADM)
- Precedence Diagramming Method (PDM)
ADM箭头图解法
AOA(活动在箭头上)
AOA(活动在箭头上)
PDM优先级图解法
(活动在节点上)
(活动在节点上)
依赖的类型
• Finish-to-start
• Start-to-start
• Finish-to-finish
• Start-to-finish
• Start-to-start
• Finish-to-finish
• Start-to-finish
4. Estimating activity durations
Duration (持续时间)包含完成活动经过的所有时间
• Effort (工作量)指完成活动的实际工作时间
• Effort (工作量)指完成活动的实际工作时间
三点评估法
Athree-point estimate
Athree-point estimate
optimistic estimate
likely estimate
pessimistic estimate
5. Developing the schedule
在排序表的基础上加入持续时间创建进度表
在排序表的基础上加入持续时间创建进度表
将上面评估出的活动持续时间汇总,创建一个真正的、用于后面管理项目的进度表
tools and techniques
Gantt charts
Critical path analysis
松弛或浮动
slack
float
slack
float
单个活动的浮动时间
PERT analysis
6. Controlling the schedule
6
项目成本管理
Project Cost Management
Project Cost Management
什么是成本(Cost)?
- 成本是只为了完成某个目标而牺牲一些资源,这些资源通常用货币来衡量
- 成本超支(Cost overrun)是实际成本超出预期的额外百分比或金额
什么是项目成本管理?
- 项目成本管理是指在批准的预算内完成项目所需要的工程
1. 估算成本
成本估算的类型
估算成本的工具和技术
与IT成本估算相关的典型问题
2. 确定预算
3. 控制成本
挣值管理
Earned Value Management (EVM)
Earned Value Management (EVM)
挣值管理术语:
- 计划价值(PV),也称预算,以前称为计划工作成本预算(BCWS),,是指在给定期间内 计划用于某项活动的已批准总成本估计中的那部分
- 实际成本(AC),以前称为实际已完成的工作成本(ACWP),是在给定期间内完成一项活动的工作所发生的总成本
- 挣值(EV),以前称为执行工作的预算成本(BCWP),是对实际完成的物理工作的价值的估计
7
项目质量管理
Project Quality Management
Project Quality Management
什么是项目质量管理?
- 项目质量管理的目的是确保项目能够满足其需要
项目质量管理流程:
- 规划质量管理(planing quality management):确定哪些质量标准与项目相关,以及如何满足这些标准;例如公制是一种测量标准
- 管理质量(managing quality):将质量管理计划转化为可执行的质量活动
- 控制质量(controlling quality):监测具体项目结果,以确保它们符合相关的质量标准
1.规划质量管理
2.质量管理
3.质量控制
质量控制相关的工具和技术
统计抽样
Statistical Sampling
Statistical Sampling
What?
统计抽样包括从总体中选择一部分作为样本(Sample size)进行检验。
样本尺寸越大,越具有代表性,样本尺寸越小,越不具有代表性
统计抽样包括从总体中选择一部分作为样本(Sample size)进行检验。
样本尺寸越大,越具有代表性,样本尺寸越小,越不具有代表性
测试
8
项目人力资源管理
Project Human Resource Management
Project Human Resource Management
领导和管理人的关键
•Motivation theories
•Effectiveness
•Leadership
- Intrinsic motivation
- Extrinsic motivation
•Effectiveness
•Leadership
`
资源分配
资源均衡
发展项目团队
• Extrovert/Introvert (E/I): draw energy from other people/yourself
• Sensation/Intuition (S/N): take in facts, details and reality/imaginative and attentive to
intuition
•Thinking/Feeling (T/F): objective and logical/subjective and personal
• Judgment/Perception (J/P): tend to establish deadlines and take them seriously/keep
things open and flexible
• Sensation/Intuition (S/N): take in facts, details and reality/imaginative and attentive to
intuition
•Thinking/Feeling (T/F): objective and logical/subjective and personal
• Judgment/Perception (J/P): tend to establish deadlines and take them seriously/keep
things open and flexible
处理冲突
9
项目沟通管理
Project Communications Management
Project Communications Management
项目沟通管理的主要流程:
- 规划项目沟通管理(Planning communications management)
- 管理沟通(Managing communications)
- 监管沟通(Monitoring communications)
可以在哪些方面提高沟通效率?
1. 关注团队和个人沟通需求
个人的偏好会影响沟通:
- 内向的人(introvert)喜欢更私密的交流,而外向的人(extrovert)喜欢在公共场合讨论事情
- 感性的人(sensing)需要循环经济的细节,而直觉型的人(intutive)喜欢理解大局
- 思考的人(thinker)想知道决策背后的逻辑,而感性的人(feeling)想知道事情是如何影响他们个人的
- 判断型的人(judge)被驱使去完成最后期限,而感知型的人(perceiving)在制定和执行计划方面需要更多的帮助
面对面沟通的重要性:
2. 使用正式和非正式的沟通方式
3. 及时、有效地传达重要信息
4. 为传达坏消息做好准备
5. 确定沟通渠道的数量
管理沟通
what?
- 管理沟通是项目经理工作的很大一部分
- 在正确的时间以有用的格式将项目信息传递给正确的人,这与首先开发信息一样重要
选择合适的沟通方式和媒体
沟通方法的分类:
- interactive communication
- push communication
- pull communication
监控项目沟通
what?
改善项目沟通的建议
- Develop better communication skills
- Run effective meetings
- Use e-mail and other technologies effectively
- Employ templates for project communications
召开有效的会议
有效地使用电子邮件、即时消息、短信和协作工具
应用模版:项目经验报告(Lessons learned reports)
10
项目风险管理
什么是项目风险?
项目风险的一般定义是一种不确定性,它可以对实现项目目标产生消极或积极的影响
- 所以项目风险不都是消极的,负面的
- 负面风险包括理解项目中可能出现的潜在问题,以及它们如何阻碍项目成功
- 积极风险是导致好事发生的风险;有时被称为机遇
项目风险管理的重要性
项目风险管理是在项目的整个生命周期中识别、分析和应对风险的艺术和科学,以达到项目目标的最佳利益
风险管理在项目中经常被忽视,但是它可以通过帮助选择好的项目、确定项目范围和开发现实的评估来帮助提高项目的成功
风险效用
risk utility
risk utility
risk-averse
risk-neutral
risk-seeking
risk-neutral
risk-seeking
项目风险管理流程
`
概率/影响矩阵充分显示了风险发生的可能性和影响
前十大风险项追踪:在项目的整个生命周期中保持对风险的意识
11
项目采购管理
Project Procurement Management
Project Procurement Management
什么是采购?
项目采购管理的流程
1.计划采购管理
决定要采购什么,以及如何获得
这一过程是确定买还是做,如果自己做能不需要采购管理
这一过程是确定买还是做,如果自己做能不需要采购管理
一些能够帮助计划采购管理的工具:
make or buy analysis
expert judgement
market research
工作陈述
Statement of Work
Statement of Work
2.实施采购
获取卖方回应,选择卖方,并授予合同
3.控制采购
管理与卖方的关系,监督合同执行情况,根据需要进行变更,并完成合同
12
项目干系人管理
project stakehoders management
project stakehoders management
项目干系人管理流程
1.规划干系人管理
确定有效吸引干系人参与的策略
2.识别干系人
确定参与项目或受项目影响的每个人,并确定管理与他们的关系的方法
3.管理干系人参与
与项目干系人沟通和合作,以满足他们的需求和期望,解决问题,并促进参与项目决策和活动
4.监管干系人参与
与项目干系人沟通和合作,以满足他们的需求和期望,解决问题,并促进参与项目决策和活动
干系人识别
干系人分类
干系人登记册
stakeholder register
stakeholder register
权利/兴趣网格
按干系人的权利和对项目的兴趣大小进行分组,以便分门别类的制定策略
干系人的参与水平
unware不知道
resistant
抵抗
抵抗
neutral
中立
中立
supportive
支持
支持
leading
领导
领导
管理干系人参与
SDLC
1.识别问题并获批
vision document
问题描述
功能
利益
2.计划项目,who,what,how [确定系统架构/确定所有子系统,]
3.识别并理解问题和需求 [对此轮循环的子系统进行需求分析]
发现并理解子系统的问题和需求
1.收集信息
2.识别用例
3.定义用例并描绘
4.设计实现
5.测试
6.整合部署